PARIS: Airbus is tentatively targeting late September for the first flight of its delayed A350F freighter as the European planemaker seeks to challenge Boeing’s longstanding dominance of the large cargo aircraft market, industry sources said Tuesday.
The planned flight could be pushed into early October, leaving Airbus with a tight certification schedule as it seeks to complete flight testing and deliver the first aircraft to customers before the end of 2027.
Industry sources said organizers are working toward a preferred flight date of September 24, although technical issues or unfavorable weather could alter the schedule.
Flight testing for a new aircraft typically takes between 12 and 15 months, according to industry sources. The timetable therefore leaves limited room for delays if Airbus is to meet its target for initial deliveries in the second half of 2027.
An Airbus spokesperson said the company had no update beyond its latest guidance, which calls for the A350F’s maiden flight before the end of 2026 and its first customer delivery in the second half of 2027.
Launched in 2021, the A350F was originally scheduled to enter service four years later. The dedicated freighter variant of Airbus’ A350 wide-body family is designed to compete in a cargo aircraft segment that has long been dominated by Boeing.
Airbus has secured orders for 107 A350F aircraft, compared with 38 orders for its smaller and older A330F freighter.
The program has faced delays, including issues involving cargo doors manufactured by Airbus in Spain, Reuters reported in May.
Aviation publication Leeham News reported this month that deliveries of the A350F could potentially be delayed until 2028, adding further uncertainty to the program’s timeline.
Source: Reuters